TES CanadaIntegrity Engineering
Discuss Your Challenges
Pressure equipment RBI assessment visual showing vessels, risk ranking, inspection planning, and interval optimization.
Case ExperienceInspection Prioritisation
LNG Facilities·Inspection Prioritisation·TES Canada Project

API 581-Based RBI Assessment for Pressure Vessels at a Canadian LNG Facility

TES Canada completed an API 581-based RBI assessment for eight pressure vessels at a Canadian LNG facility, supporting continued operation, inspection prioritization, and vessel-specific integrity plans while reducing unnecessary intrusive inspection.

Pressure VesselsPiping SystemsRBI & Integrity ManagementFFS & Damage AssessmentAdvanced NDT ApplicationsAnonymised
RBIAPI 581Pressure VesselsLNGAsset IntegrityRisk AssessmentNon-Intrusive InspectionIntegrity Management PlanAPI 571API 580ASME PCC-3CUIBrittle FractureDamage Mechanism ReviewInspection Optimisation

A Canadian LNG production and storage facility operated a group of pressure vessels — including vessels in flammable vapour, liquid, and multiphase service — that had not been inspected during a previous scheduled shutdown. Access constraints related to insulation, coating, and fireproofing condition, combined with operational limitations, had prevented inspection from proceeding as planned.

The operator needed to understand whether the vessels could remain safely in operation through to the next available inspection window, whether projected risk would remain within the facility's tolerable risk criteria, and what future inspection or mitigation actions would be required. The objective was a technically defensible integrity basis — not a conservative assumption that would force unnecessary intrusive inspection or an unplanned outage.

The central challenge was establishing a credible, defensible integrity basis for eight pressure vessels without the benefit of recent internal inspection data. The absence of inspection data introduces uncertainty into probability of failure assessments — and that uncertainty must be managed through conservative assumptions, sensitivity analysis, and targeted confirmatory actions rather than ignored.

Several vessels were insulated or had coating and fireproofing systems whose condition could not be directly verified without removal, introducing additional uncertainty around external degradation mechanisms including Corrosion Under Insulation and atmospheric corrosion. For stainless steel insulated vessels, chloride stress corrosion cracking under insulation was a credible mechanism requiring specific assessment consideration.

The assessment needed to cover a pilot scope of eight vessels — each with distinct service conditions, materials of construction, inspection histories, and degradation profiles — while maintaining methodological consistency and producing actionable, vessel-specific integrity management plans.

LNG pressure vessels can carry high consequence potential due to the flammable and hazardous nature of process fluids. High consequence combined with data uncertainty creates a challenging assessment environment — conservative assumptions must be applied, but excessive conservatism produces misleading risk rankings and drives unnecessary inspection activity.

The damage mechanism landscape for LNG pressure vessels is broad. Internal thinning, external atmospheric corrosion, Corrosion Under Insulation, CUI chloride stress corrosion cracking for applicable stainless steel vessels, and brittle fracture considerations for low-temperature service all required systematic screening and credibility assessment — not a generic software template exercise.

Coating and fireproofing condition on several vessels could not be directly confirmed, introducing conservatism into external corrosion and CUI assessments. Managing this uncertainty required sensitivity analysis to identify which assumptions were driving risk results and to define targeted confirmatory inspection actions that could validate or improve those assumptions.

Non-intrusive inspection methods needed to be identified and prioritised where feasible — but the suitability of each technique depends on vessel geometry, insulation type, access configuration, and the specific damage mechanism being targeted. Matching inspection method to mechanism required engineering judgement beyond standard software outputs.

TES Canada structured the engagement as a three-phase RBI program, progressing from data foundation through risk assessment to integrity action planning.

Phase 1 — Data Gathering, Gap Assessment, and Asset Register Development: TES Canada reviewed available design, fabrication, operating, inspection, process, and consequence data for each vessel. Data gaps were identified and resolved through clarification with the client or addressed through conservative engineering assumptions. Vessel-specific datasets and assessment assumptions were documented. Where vessels contained multiple components with distinct degradation profiles, assessment components were defined to ensure appropriate resolution of the risk calculation.

Phase 2 — API 581 Risk Assessment: A damage mechanism review was conducted for each vessel using API 581 and API 571 logic, supplemented by subject matter expert judgement. Credible damage mechanisms were identified — including internal metal loss and thinning, external atmospheric corrosion, Corrosion Under Insulation, CUI chloride stress corrosion cracking for applicable insulated stainless steel vessels, and brittle fracture considerations where low-temperature excursion scenarios were relevant. Probability of Failure was calculated using API 581 methodology and projected over a long-term time horizon. Consequence of Failure was assessed for each vessel relative to its service fluid, inventory, and operating conditions. Risk was calculated as the product of PoF and CoF and compared against the client's risk matrix and tolerable risk criteria. Sensitivity analysis was conducted to identify the key risk drivers and quantify the impact of conservative assumptions.

Phase 3 — Integrity Action Planning and Inspection Strategy: Vessel-specific future integrity management plans were developed, incorporating confirmatory inspection and monitoring actions targeted at the identified risk drivers. Non-intrusive inspection methods were prioritised where technically feasible — including digital radiography at selected nozzle and potential metal loss locations, consideration of neutron backscatter, pulsed eddy current, PECA, tangential radiography, and UT profiling. External inspection of insulation and coating or fireproofing condition was recommended for vessels where external degradation mechanisms were the primary risk driver. Inspection drawings and defined future inspection requirements were produced for each vessel.

Engineering Disciplines
Risk-Based InspectionPressure Equipment IntegrityDamage Mechanism AssessmentCorrosion EngineeringFitness-for-ServiceNon-Intrusive Inspection PlanningAsset Integrity Management
Inspection / Assessment Methods
API 581 Probability of Failure (PoF) AssessmentAPI 581 Consequence of Failure (CoF) AssessmentAPI 571 Damage Mechanism ReviewTime-Series Risk ProjectionSensitivity AnalysisRisk Matrix Comparison Against Tolerable Risk CriteriaDigital Radiography (selected nozzles and metal loss locations)Neutron Backscatter / Pulsed Eddy Current / PECA (NII options)External Insulation and Coating Condition InspectionHoliday Testing (ASTM D5162 / ASTM G62)

TES Canada converted an inspection access challenge into a structured, defensible integrity risk assessment. A pilot scope of eight pressure vessels was assessed under API 581 methodology, with vessel-specific datasets, damage mechanism reviews, and risk calculations produced for each asset.

All assessed vessels were demonstrated to be within the client's tolerable risk range at the time of assessment. Conservative assumptions were applied where data uncertainty existed, and sensitivity analysis identified the specific assumptions driving risk results — providing the operator with a clear picture of where confirmatory inspection would have the greatest impact on risk confidence.

Vessel-specific future integrity management plans were produced, prioritising non-intrusive inspection techniques and defining action windows for future confirmatory inspections. The assessment reduced unnecessary intrusive inspection by providing a technical basis for deferring internal access where risk remained within acceptable limits, while ensuring that targeted confirmatory actions were defined to validate key assumptions. The pilot framework established a reusable methodology for extending RBI to the wider vessel population at the facility.

01

The absence of recent inspection data does not prevent a defensible RBI assessment — it changes how uncertainty is managed. Conservative assumptions, sensitivity analysis, and targeted confirmatory actions are the engineering tools for managing data gaps, not reasons to default to blanket intrusive inspection.

02

Damage mechanism reviews for LNG pressure vessels must be led by experienced integrity engineers, not delegated to software defaults. The credibility screening for CUI chloride SCC on insulated stainless steel vessels, and brittle fracture considerations for low-temperature service, requires judgement that generic software logic does not reliably provide.

03

Sensitivity analysis is not optional in a data-uncertain RBI assessment — it is the mechanism by which the assessment identifies where confirmatory inspection will have the greatest impact on risk confidence. Without it, the action plan lacks the prioritisation logic that makes it useful.

04

Non-intrusive inspection method selection requires matching technique to mechanism and geometry. Recommending NII without that matching exercise produces an action plan that looks complete on paper but may be technically inappropriate for the actual inspection challenge at each vessel.

Discuss a Similar Challenge

Facing a Similar
Integrity Challenge?

TES brings practical engineering thinking to the integrity challenges that aging infrastructure and operational pressure create. If this case experience resonates with a challenge you are navigating, a technical discussion is the right first step.